We are pleased to provide the latest update on the Classroom Replacement Project at South Shores VAPA Magnet Elementary School. The construction team has made significant progress and is excited to announce that construction will be completed this summer 2024. The new two-story classroom building was finished in January 2024 and is now in use by staff and students. Additionally, the removal of the portable classroom buildings was completed in early June 2024. Following a recent inspection of the auditorium, structural issues were identified and have since been resolved through critical repairs. We are happy to announce that the auditorium is now in use for school activities. We appreciate the support and understanding shown by our parents, community, and school administration throughout this process.
ncwebposting